I was wondering if there was a way to use the format of archive tags from taskpaper 2.
For example, when archiving the following:
task 1:
subtask 2:
- item 1
when archived in taskpaper 3 item 1 shows up as:
- item 1 @done(2016-04-28) @project(subtask 2)
whereas in taskpaper 2 it would show up as
- item 1@done(2016-04-28) @project(task 1 /subtask 2)
So I’m wondering if there is a way to make taskpaper 3 function like taskpaper 2 did in this regard.